Basin Stories
New Bridges on Bateman Creek
by April Olbrich
 |
The bridge in November 2006
Photo: Tom Murtagh |
This spring, native winter steelhead trout and native
cutthroat trout on Gales Creek will have
access to additional spawning and rearing
areas on Bateman Creek. Two new bridges,
eliminating fish passage barrier culverts
were constructed in September 2006 on Bateman Creek,
a tributary to Gales Creek. One bridge was constructed
by Oregon Department of Transportation (ODOT), the other
by cousins Steve and Dave Bateman, with help from Paul
Johnson, NW Steelheaders member, Bernadette Graham-Hudson,
Oregon Department of Fish and Wildlife (ODFW) stream
restoration biologist and April Olbrich, Tualatin River
Watershed Council coordinator. Bateman Creek enters
Gales Creek, a prime winter steelhead and cutthroat
stream, on the east side of Highway 6, immediately adjacent
to the new bridge.
The Bateman family has owned and been
involved with forested lands in northwestern
Washington County since 1885. Currently,
the family owns 170 acres of forested lands through
which Bateman Creek runs. There are four stream crossings,
all culverts, of Bateman Creek on the property. In 2005,
the Bateman Tree Farm received the Washington County
Small Woodlands Association’s
(WCSWA) Tree Farm of the Year award for
its management practices.
When ODOT began its construction of
a bridge over Bateman Creek on Highway
6 near Glenwood, the Bateman family’s ears perked
up. The new ODOT bridge replaced a culvert
and a nonfunctioning fish ladder that
were blocking fish passage from Gales
Creek into Bateman Creek.
 |
Bateman Creek culverts that were removed and replaced with
a bridge
Photo: Paul Johnson |
Steve Bateman, a family member, had a vision to
replace culverts with concrete bridges
over the stream crossings on the family property.
This vision included providing fish passage
by eliminating a fish passage barrier
culvert as well as eliminating future culvert maintenance
and providing sustainable road crossings for the family’s
future timber harvesting operations. Bateman
met Graham-Hudson in 2005 when the two
discussed Bateman supplying large wood for in-stream
habitat projects. Graham-Hudson works
with private landowners, watershed councils and other
entities to identify and implement habitat restoration
projects.
The opportunity
presented itself when he and Bernadette
Graham-Hudson learned of the ODOT bridge
replacement. “Because
ODOT was removing the fish passage barrier
at the mouth of Bateman Creek, it made
sense to replace the next upstream barrier,
which was a set of culverts on the Bateman
property. These two projects complement
each other and together, open up additional
spawning and rearing habitat for native
fish in this area,”
Graham-Hudson said.
The pair joined up with April Olbrich, coordinator
of the Tualatin River Watershed Council. The watershed
council is composed of diverse multiple stakeholder
groups in the Tualatin Basin, who work together to promote
and improve watershed health in the basin. Olbrich said, “Gales
Creek watershed is one of the basin’s best streams
for native cutthroat and federally listed native winter
steelhead trout. The Council is also focusing its efforts
downstream to work with private landowners, on improving
stream habitat and water quality in a five mile stream
reach between the Gales Creek community and Watts Bridge
(Stringtown Road). Working to remove the culvert and
replace it with a bridge on the Bateman property at
the same time that ODOT was building the bridge complemented
the Council’s work downstream.”
 |
Dave Bateman builds the forms into which the
concrete will be poured for the bridge footings.
Photo: Paul Johnson |
The three wanted to complete the closest culvert replacement
in the same time frame as the ODOT bridge project in
order to maximize the benefits of both projects. They
began looking for funding sources and at the costs of
concrete span bridges. The price for a new concrete
span bridge was beyond the project budget, but an opportunity
to purchase three used concrete slabs came about. J.W.
Fowler Co. was overseeing the construction of the ODOT
Bateman Creek bridge, but was also replacing a bridge
over the Columbia Slough in Portland. Bateman and Fowler’s
construction supervisor talked. The concrete slabs needed
to have at least a 30-year useful life and be able to
handle weighs of 45 tons required for logs trucking
for future harvesting opportunities. The team needed
helping in evaluating the concrete slabs and making
sure that the bridge could handle the necessary weights.
Enter Paul Johnson, former ODFW chief engineer and
a retired surveyor and structural engineer,
who volunteers with the Association
of Northwest Steelheaders – Tualatin
Valley Chapter. The Tualatin Valley Chapter of the
Association of Northwest Steelheaders is a fishing and
restoration organization that works on projects throughout
northwestern Oregon that improve stream conditions for
steelhead and cutthroat trout. Paul and Dennis Rychlik,
another Tualatin Valley chapter Steelheaders member,
evaluated the concrete slabs and provided drawings and
oversight on the bridge footings. Bateman owned some
of the necessary heavy equipment and could provide much
of the labor required, including removing the existing
culverts, building the bridge footings and placing the
concrete spans on the bridge footings. Oregon Department
of Forestry regulates this type of activity on forested
lands working with ODFW.
 |
Steve Bateman guides the final bridge slab into place as
Doug Ranes operates the track log loader
Photo: Paul Johnson |
The trio sought funding an Oregon Watershed Enhancement
Board (OWEB) Small Grant program. This program provides
funding for up to $10,000 for on-the-ground restoration
projects approved by the local OWEB small grant team
and OWEB. These grants require a 25% cash or in-kind
match by the landowner. The team and OWEB evaluate grant
applications based on its watershed criteria and priorities,
and if approved, funding is generally available within
60 days. The OWEB grant would provide funds to purchase
and transport the concrete slabs, as well as to build
the bridge footings. It would also pay for numerous
materials necessary to implement the project including
erosion control materials and additional heavy equipment
needed to lift the 12,000 concrete slabs onto the bridge
footings. A grant application was submitted in mid-April
2006 and approved in June 2006.
The work began in late July when the concrete slabs
were delivered to the site. Dave Bateman, Steve’s cousin and a surveyor, participated in surveying the bridge location and helped build the
forms. Paul Johnson and Bernadette Graham-Hudson were
on-site working with the Bateman cousins starting in
August. Prior to the culvert removal, Graham-Hudson
isolated the work area by re-routing the stream through
a temporary culvert. Nets were placed around the work
area to prevent fish from entering the work site and
fish were removed from the project area by electrofishing.
Twenty-two cutthroat trout were removed and relocated
out of the impact area.
 |
The slabs and bolt in place complete the bridge
Photo:
Paul Johnson |
In mid-September, Doug Ranes, NW Thinning Systems,
owner of a large track log loader was hired to place
the three bridge slabs on the bridge footings. The two
large machines worked in tandem to align the slabs once
placed on the footings. The work finished up in September
with the bridge guardrails to be installed by Bateman
this coming spring. Bateman will also be planting trees
in February near the bridge crossing. A fish survey
will be conducted in 2007 and future years to determine
the success of both projects.
All those participating were pleased. The partners
hope to tackle other upstream crossings in the future.
|